Circuit breaker GTP check against the tender specification
To check a circuit breaker GTP, compare each value the vendor guarantees with the requirement in the tender specification: ratings, insulation levels, short-circuit performance and auxiliary details. GridFlo does this automatically for 18 circuit breaker parameters and returns a deviation sheet with the clause and page for each finding.
- Also covers: VCB, SF6 breaker, vacuum circuit breaker, 33 kV to 765 kV
- Typical standard: IEC 62271-100 / IS 13118
- Text and scanned PDF specifications
What GridFlo checks in a circuit breaker GTP
These 18 parameters are compared with your specification. Anything else in the vendor's sheet is left for the engineer.
| Parameter | Unit |
|---|---|
| Rated voltage (Um) | kV |
| Rated frequency | Hz |
| Minimum creepage distance | mm/kV |
| Lightning impulse withstand voltage | kVp |
| Power frequency withstand voltage (1 min) | kV |
| Short-time withstand current | kA |
| Short-time current duration | s |
| Applicable standard | – |
| Rated normal current | A |
| Rated short-circuit breaking current | kA |
| Rated short-circuit making current | kAp |
| Switching impulse withstand voltage | kVp |
| Total break time | ms |
| Rated operating sequence | – |
| First pole to clear factor | pu |
| Auxiliary / control DC voltage | V |
| Interrupting medium | – |
| Mechanical endurance class | – |
Deviations vendors commonly make
- Short-time current duration offered as 1 s where the specification asks for 3 s.
- Total break time longer than the limit, often hidden by a change of unit (65 ms offered against 3 cycles = 60 ms).
- Trip and close coil voltage that doesn't match the substation's DC system (110 V offered against 48 V or 220 V).
- Operating sequence without rapid auto-reclose duty (CO-15 s-CO offered against O-0.3 s-CO-3 min-CO).
- Mechanical endurance class answered with "as per IEC" and no class stated.
- Creepage distance stated in mm when the specification gives mm/kV, or the other way round.
How the check works
- Upload the tender specification as a PDF. Several documents can be combined, for example an equipment specification and a general ratings specification.
- Upload the vendor's GTP in Excel or CSV, in whatever layout the vendor used.
- Choose "Circuit breaker" and the system voltage.
- Review the result. Each value is marked complies, deviation, not furnished or to verify, with the sentence from the specification beside it. Download the deviation sheet and the vendor comments.
AI is used only to read the specification. The pass or fail decision is made by fixed engineering rules that convert units and know which direction is safe. When the specification is unclear or contradicts itself, the item is flagged for an engineer and never passed silently.
Frequently asked questions
Can GridFlo check a circuit breaker GTP against a scanned specification?
Yes. Scanned pages are read as images. Values read from scans are marked for the engineer to confirm.
Which circuit breaker standards does it work with?
GridFlo checks against whatever your tender specification requires, so it works with specifications based on IEC 62271-100 / IS 13118 and utility-specific requirements. It does not need the text of the standard.
How long does a check take?
One to three minutes for a new specification. Further vendor GTPs against the same specification are checked in seconds.
Is it accurate?
On 13 test cases from public Indian and UK utility specifications, GridFlo read 97 of 97 specified values correctly and invented none. It is a first pass for an engineer, who makes the final decision.