GridFlo › Power transformer GTP check

Power transformer GTP check against the tender specification

By the GridFlo team at Hyzync · Updated

To check a power transformer GTP, compare each value the vendor guarantees with the requirement in the tender specification: ratings, insulation levels, short-circuit performance and auxiliary details. GridFlo does this automatically for 28 power transformer parameters and returns a deviation sheet with the clause and page for each finding.

What GridFlo checks in a power transformer GTP

These 28 parameters are compared with your specification. Anything else in the vendor's sheet is left for the engineer.

ParameterUnit
Rated frequencyHz
Minimum creepage distancemm/kV
Applicable standard–
Rated powerMVA
HV rated (no-load) voltagekV
LV rated (no-load) voltagekV
Tertiary rated voltagekV
Vector group–
Type of cooling–
Percentage impedance (principal tap)%
No-load losskW
Load loss at rated currentkW
Auxiliary losskW
Tap range–
Number of tap stepsnos
Tap changer type–
Top oil temperature riseK
Average winding temperature riseK
Noise leveldB
Lightning impulse withstand - HVkVp
Lightning impulse withstand - LVkVp
Lightning impulse withstand - neutralkVp
Switching impulse withstand - HVkVp
Power frequency withstand - HVkV
Power frequency withstand - LVkV
Maximum flux densityT
Maximum current densityA/mm2
Short-circuit withstand durations

Deviations vendors commonly make

How the check works

  1. Upload the tender specification as a PDF. Several documents can be combined, for example an equipment specification and a general ratings specification.
  2. Upload the vendor's GTP in Excel or CSV, in whatever layout the vendor used.
  3. Choose "Power transformer" and the system voltage.
  4. Review the result. Each value is marked complies, deviation, not furnished or to verify, with the sentence from the specification beside it. Download the deviation sheet and the vendor comments.

AI is used only to read the specification. The pass or fail decision is made by fixed engineering rules that convert units and know which direction is safe. When the specification is unclear or contradicts itself, the item is flagged for an engineer and never passed silently.

Frequently asked questions

Can GridFlo check a power transformer GTP against a scanned specification?

Yes. Scanned pages are read as images. Values read from scans are marked for the engineer to confirm.

Which power transformer standards does it work with?

GridFlo checks against whatever your tender specification requires, so it works with specifications based on IEC 60076 / IS 2026 and utility-specific requirements. It does not need the text of the standard.

How long does a check take?

One to three minutes for a new specification. Further vendor GTPs against the same specification are checked in seconds.

Is it accurate?

On 13 test cases from public Indian and UK utility specifications, GridFlo read 97 of 97 specified values correctly and invented none. It is a first pass for an engineer, who makes the final decision.

Check your next GTP in minutes

5 free checks. No card needed. Try it on our sample tender in one click.