GridFlo › Deviation Sheet for Vendor GTP Review
How to prepare a deviation sheet for a vendor GTP
A deviation sheet lists every point where a vendor's offer differs from the tender specification. Each row names the parameter, the specified value with its clause and page, the value the vendor offered, and the status: complies, deviates, or not provided.
Columns of a good deviation sheet
| Column | What goes in it |
|---|---|
| Parameter | The item being checked, e.g. short-time current duration |
| Specification requires | The required value and unit, e.g. 3 s |
| Reference | Clause and page of the specification, so anyone can verify it |
| Vendor offers | The value in the vendor's GTP, e.g. 1 s |
| Status | Complies, deviation, not furnished, or to verify |
| Comment / decision | What the vendor must do, or why the deviation is accepted |
Example: 33 kV vacuum circuit breaker
| Parameter | Specification | Vendor offers | Status |
|---|---|---|---|
| Short-time current duration | 3 s (cl. 5.0) | 1 s | Deviation |
| Total break time | ≤ 3 cycles = 60 ms (cl. 5.2) | 65 ms | Deviation |
| Control voltage | 48 V DC (cl. 5.2) | 110 V | Deviation |
| Mechanical endurance class | Per IEC 62271-100 | "as per IEC" | Not furnished |
| Lightning impulse withstand | 170 kVp | 170 kVp | Complies |
Rules that avoid mistakes
- Convert units before comparing. 3 cycles at 50 Hz is 60 ms; kV rms is not kV peak; mm is not mm/kV.
- Know the direction. A higher withstand voltage is acceptable; a longer break time is not.
- Treat "as per IEC" as missing. A guarantee needs a value.
- Always give the clause. A comment without a reference invites argument.
- When the specification contradicts itself, flag it. Do not pick one value silently.
Preparing it automatically
GridFlo prepares the deviation sheet from the two documents. Upload the tender specification PDF and the vendor's GTP in Excel; it reads the requirements, applies the rules above, links every row to the exact sentence in the specification, and exports the deviation sheet and a comment sheet in Excel. Engineers then accept, reject or annotate each row.
Frequently asked questions
What is the difference between a deviation sheet and a comment sheet?
A deviation sheet lists every difference between the offer and the specification. A comment sheet (or comment resolution sheet) is what you send to the vendor: only the points they must correct, with space for their reply.
Who prepares the deviation sheet?
Sometimes the vendor declares deviations in the bid. In practice the EPC contractor's or consultant's engineer prepares one by checking the GTP against the specification, because undeclared deviations are common.
How long does a deviation sheet take to prepare?
By hand, a few hours per document for a careful engineer. GridFlo produces a first-pass deviation sheet in one to three minutes, which the engineer then reviews.